ELEMENTAL COST ANALYSIS - FORM 3 8 - Residential Buildings
A - 21 - 24,425
Gross Floor Area : SUMMARY OF ELEMENT COSTS Tender date : March 2012
24,425 m2
ELEMENT SPECIFICATION
1 Substructure Precast Concrete Spun Pile with 600mm diameter pile. (Under separate contract)
1A Piling Vibrated Reinforced Concrete in pile caps, column stumps, lift pits, ground beam, ground slab,
1B Work Below Lowest Floor lift pit wall and slab.
Finish
2 Superstructure Vibrated Reinforced Concrete in column, suspended floor beam, lift core wall and water tank
2A Frame wall.
2B Upper Floors Vibrated Reinforced Concrete suspended floor slab.
2C Roof Vibrated Reinforced Concrete suspended roof slab & roof beam, Reinforced concrete flat roof
with reinforced concrete gutter and UPVC rainwater down pipe.
2D Staircase Proprietary steel roof truss with metal deck roof covering
Vibrated Reinforced Concrete in staircase, landing beam and slab, mild steel railing and and
2E External Walls balustrading. Cement render with non-slip nosing tiles to staircase, skim coating with painting to
2F Windows & External Doors soffit of staircase
2G Internal Walls and Partition 115mm and 230mm thick common clay brick wall with reinforcement and 115mm thick parapet
2H Internal Doors wall with reinforcement in cement and sand (1:3) mortar.
Aluminium door, timber flush door, roller shutter door, aluminium framed window and aluminium
framed louvred window.
115mm and 230mm thick common clay brick wall with reinforcement in cement and sand (1:3) mortar.
Aluminium door, timber flush door, fire rate solid timber door, roller shutter, fibre reinforced
plastic(FRP) composite door and PVC folding door.
3 Finishes Ceramic wall tiles to bathrooms, plaster and paint.
3A Internal Wall Finishes Timber flooring to bedroom , Ceramic floor tiles to apartment unit and cement and sand paving to
3B Internal Floor Finishes M & E Rooms.
Cemboard, waterproofed fibre cement ceiling board, skim coating and painting.
3C Internal Ceiling Finishes Cement and sand plastering and weathershield painting.
3D External Finishes
4 Fittings and Furnishing Not applicable
5 Services Pedestal water closet, squatting pan, wall hung basin, kitchen sink, toilet paper holder, shower
5A Sanitary Appliances set and soap holder, bib tap, kitchen tap and floor trap.
Cold water piling with water tank to each units and sanitary piping.
5B Plumbing Installation
5C Refuse Disposal Not Applicable.
5D Air Conditioning & Single Split Interval air conditioning units to be provided to all residential units. Indoor unit of wall
mounted type to be provided for living & dining room and all bedrooms. Mechanical ventilation
Ventilation System system to be provided for common area, M&E room, public toilet and etc. All toilet and
bathrooms in the apartment units to be naturraly ventilated with external window.
5E Electrical Installation Electrical wiring excluding fittings, light and fan points, telephone wiring and points
5F Fire Protection Installation Hose reel system, wet riser system.
5G Lift & Conveyor Installation Lift
5H Communication Installation Not applicable
5J Special Installation Not applicable
5K Builder's Profit & Attendance 3% of total Prime Cost Sums as Builder's profit and attendance for all prime cost sum
on Services Not applicable
5L Builder's Work in Connection
with Services
6 External Works Premix roadwork, mosaic tiles and non-slip homogeneous tiles for landcaping area.
6A Site Work 300mm Diameter pipe culvert, 225mm diameter half round glazed ware drain, 225mm Vitrified
6B Drainage clay pipe sewerage pipe and mild steel grating
Not applicable.
6C External Services Not applicable.
6D Ancillary Buildings Not applicable.
6E Recreational Facilities