Page 56 - Surveyor 54.3 and 4
P. 56

PROFESSIONAL PRACTICE
        The Malaysian Surveyor



        1.  Whether CIPAA applies retrospectively to           main ground that there was a breach of natural justice
           construction contracts entered into before CIPAA, i.e.   when the adjudicator refused to consider the cross
           15th April 2014?                                    contractual set off.
        2.  If CIPAA applies retrospectively, does section 35 also
           apply retrospectively to all construction contracts   High Court & Court of Appeal
           entered into before CIPAA i.e. 15th April 2014?     The High Court found for PWC Corporation and held
                                                               that the adjudicator was right in declining jurisdiction
        It was held that CIPAA applies prospectively as it affects
        substantive rights of parties by providing an additional   over and beyond the project/contract before him given
        avenue for parties to commence legal actions to claim   that the other two contracts were before different
        for monies due and not just a mere change of forum     adjudicators. This was also affirmed by the Court of
        (from court or arbitration to adjudication). It creates a   Appeal. The arguments that CIPAA applies prospectively
        new avenue for access to justice and is not merely a   were raised by Ireka in the Court of Appeal.
        procedural legislation as the procedural regime exists as   Ireka appealed to the Federal Court.
        a by-product of this substantive right.

        Hence in so far as Section 35 of CIPAA is concerned, it   Federal Court
        prohibits parties to rely upon payment arrangements. Its   The same quorum who heard Jack-In Pile heard the
        applicability is prospective as well and cannot be relied   current appeal and decided (on the same grounds)
        on to void the pay-when-paid clause entered into before   that CIPAA applies prospectively. The Federal Court did
        15th April 2014.                                       not address the cross contractual set off issue which
                                                               remains alive today.
        The Federal Court also considered Sections 2, 3 and
        41 of CIPAA which set out the applicability and non-
        applicability of CIPAA. The Federal Court concluded that   Future Outlook
        Parliament would have included an express section in
        CIPAA if it was intended to apply retrospectively.     The Federal Court’s decisions in Jack-In Pile and Ireka
                                                               impacted the construction industry where all parties
        Ireka Engineering & Construction                       with construction contracts entered into before 15th
                                                               April 2014 can no longer resort to statutory adjudication
        Sdn Bhd v PWC Corporation Sdn                          under CIPAA. It was also stressed that a retrospective
        Bhd and Two Other Appeal Cases                         application would prejudicially affect vested rights of
                                                               the parties or the legality of the transaction under the
                                                               contract.
        Background
                                                               However, the Federal Court’s decisions have created
        In the case of Ireka Engineering, Ireka appointed PWC   practical difficulties and uncertainties, particularly
        Corporation under three contracts for construction     in relation to the recovery of monies paid out under
        projects in Mont Kiara, Sandakan and KL Sentral        adjudication decisions which will now be rendered void.
        respectively, all of which were entered into before CIPAA   For example:
        came into force.
                                                               Adjudication Decisions based on contracts entered into
        Disputes arose under the three projects and PWC        before 15th April 2014 and enforced as judgments in the
        Corporation initiated adjudication proceedings against   High Court are now void. The following predicaments
        Ireka. Ireka’s primary defence and / or cross claim in the   may be encountered by affected parties:
        adjudication proceedings was that it had a right to set
        off any amount claimed by PWC Corporation against any   a.  The avenues to recover the adjudicated sum paid out
        amount due or liable to be paid by PWC across all three   will likely be through the initiation of arbitration or
        projects (“cross contractual set off”).                   court proceedings.

        The adjudicator in delivering a decision in favour of PWC   b.  The legal recourse for the principal / employer to
        Corporation, decided that he had no jurisdiction over     recover monies paid pursuant to Section 30 of CIPAA
        disputes arising out of the other projects and contracts   where the wining party receives payment directly
        as they concerned other contracts and the disputes were   from the principal / employer is unclear.
        before two other adjudicators.                         c.  The legal recourse for companies wound up premised
        PWC applied to enforce the adjudication decision. Ireka   on a now void adjudication decision is unclear.
        applied to set aside the adjudication decision on the

         56
   51   52   53   54   55   56   57   58   59   60   61